Pipeline View Executive View
Production Pipeline Intelligence

5-Stage Production
Pipeline Dashboard

End-to-end visibility from Persiapan to Finishing ? GM & Director Level

05 May 2026 13 Jul 2026 14 Jul 2026
Data Source: Operational logs & daily WhatsApp production reporting
Filter:
05 May, 13 Jul, 14 Jul 2026 (Baseline Audit)
Total Output
223,600
pcs/sheets (3-day)
Avg Daily
74,533
per day average
Active Machines
11/14
avg running
Downtime
18%
OFF/idle rate
Bottleneck
F2
Finishing 2 constraint
Production Flow

5-Stage Pipeline Overview

Stage 1

Persiapan

Preparation

Wohlenberg Die Cut Tinta
Status:Active
Jobs:10 tracked
Stage 2

Pra Cetak

Pre-Press

CTP Eye C
Status:Limited
Data:N/A
Stage 3

Offset Printing

CD & CX

CD 102 CX 104
Output:53,300
Status:Variable
Stage 4

Finishing 1

UV, Lam, Hotstamp

UV 1 UV 2 Youbond
Status:Bottleneck
Util:22%
Stage 5

Finishing 2

Diecut, Inspect, Pack

MK Novacut Diana Ambition Rolam
Output:142,900
Status:Mixed
Stage Throughput

Daily Output by Pipeline Stage

-66% (13?14 Jul)
Constraint Analysis

Pipeline Bottleneck Heatmap

Activity Mix

Job Status Distribution

Machine Detail

Activity Log by Pipeline Stage

Viewing 3-Day Sample Baseline
Stage Machine 05 May 13 Jul 14 Jul Trend
S1: Persiapan WohlenbergCutting SBPDCGP, HallmarkIntermittent
Die CutSupport
Tinta3 jobs RI3 jobs RI4 jobs (3 RI)Consistent
S2: Pra Cetak CTPNot reported
Eye C ProfilerNot reported
S3: Offset CD 10214,000Setting5,000Variable
CX 10410,00012,3002,000Declining
S4: Finishing 1 UV Shengshun 1Shift 3MJCMostly Down
UV Shengshun 2Shift 3MJCMostly Down
Youbond (Lam)1,900OFFOFFChronic Idle
S5: Finishing 2 MK (Diecut)OFF (sparepart)2,40010,000Recovering
Novacut (Diecut)36,000SettingSettingSetup-heavy
Diana EyeOFFOFFSettingMostly Down
Ambition (FG)52,00043,000Selesai+SettingTop Performer
Rolam (FG)Setting21,50014,000Ramping Up
Packing Manual/Gaplok5 tasks5 tasks8 tasksHigh Load
Executive Takeaways

Pipeline Health & Critical Insights

Critical: Finishing 1 is Pipeline Blocker

Stage 4 (UV, Youbond) at 22% utilization. All 3 machines OFF or idle on 14 Jul. This creates a bottleneck preventing printed sheets from flowing to Finishing 2. Work-in-progress is likely piling up before this stage.

66% Output Collapse on 14 Jul

Total output dropped from 80,200 (13 Jul) to 27,000 (14 Jul). Root cause: Finishing 1 machines (UV1, UV2, Youbond) all OFF simultaneously. This is not a demand issue ? it's a capacity failure at a critical pipeline stage.

Diana Eye (Inspection) Chronic Underutilization

Automatic inspection machine OFF 2 of 3 days. If Diana Eye is down, quality inspection falls back to manual ? slowing Finishing 2 throughput and increasing defect escape risk. Maintenance review required.

Ambition (Folder Gluer) is Anchor Machine

Delivered 95,000+ pcs across 2 active days ? 42% of total output. As the primary folder gluer in Finishing 2, Ambition is the backbone. Preventive maintenance must be priority #1 to protect this capacity.

Pipeline Imbalance: Printing vs Finishing

Stage 3 (Offset) produced 53,300 pcs but Stage 4 (Finishing 1) can't keep up. This creates WIP inventory buildup between stages. Consider outsourcing more Finishing 1 work (hotstamp, emboss already outsourced) or adding shifts to UV/Youbond.

Manual Packing Section Overloaded

Manual tasks increased from 5 to 8 across 3 days. As automated machines (Diana Eye, UV) go down, work shifts to manual. This is a leading indicator of labor cost escalation and quality risk. Automation investment needed.

MK Recovery Post-Downtime

MK went from OFF (waiting for sparepart belt timing) on 05 May to 10,000 pcs on 14 Jul. Good recovery. However, Novacut (also diecut) spent 2 of 3 days in "setting" ? review whether changeover time can be reduced.

Data Gap: Stage 2 (Pra Cetak) Not Reported

CTP and Eye C Profiler are not appearing in WhatsApp reports. Either they run silently, or operators aren't reporting them. This creates a blind spot ? GM cannot see pre-press throughput or identify delays before printing starts.

For GM / Director Review

Recommended Actions

Fix Finishing 1

Immediate maintenance audit on UV1, UV2, Youbond. This is the #1 bottleneck. Consider outsourcing UV work if machines can't be restored.

Root Cause 14 Jul

Request incident report from production supervisor. Why were all Finishing 1 machines OFF simultaneously? Material? Manpower? Breakdown?

Standardize Reporting

Mandate all stages (including CTP, Eye C) in WhatsApp reports. Current blind spots prevent full pipeline visibility. Create a template.

Reduce Manual Dependency

Manual packing workload trending up. Evaluate ROI on automation for sorting, gluing, and packing. Also fix Diana Eye to restore auto-inspection.